B-230604:
Jun 30, 1988
A firm protested an Air Force contract award for a missile disassembly facility, contending that the Air Force: (1) improperly deleted an item and its funding after bid opening, which displaced it as the low bidder; and (2) should reimburse it for its bid and protest preparation costs. GAO held that the Air Force: (1) improperly displaced the protester as the low bidder after bid opening; (2) shou...