The report you requested was not found, or there is more than one product with this report number. Please select from this list of similar report numbers.


[Protest of Army Rejection of Bid]

B-230379: Feb 12, 1988

A firm protested the Army's rejection of its bid as nonresponsive, contending that the Army should have accepted its late acknowledgement of a solicitation amendment as a bid modification, since its bid was low and otherwise responsive. GAO held that the Army properly rejected the bid, since: (1) it failed to acknowledge the amended delivery date, which was a material change; and (2) acceptance of...

  • pdf icon View Decision (PDF, 2 pages)
B-230379, Feb 12, 1988

B-230379: Feb 12, 1988

An amendment to the solicitation which alters the delivery date under the contract is material and a bidder's failure to acknowledge such amendment renders its bid nonresponsive. 2. A late acknowledgment of a material amendment may not be accepted as a late modification of an otherwise successful bid since the bid as originally submitted is nonresponsive. S.K. argues that the Army should have waiv...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap