[Protest of Air Force Contract Award for Turbine Rotor Bucket Blades]

B-230088: Apr 11, 1988

A firm protested an Air Force contract award for turbine rotor bucket blades, contending that the Air Force failed to send it: (1) the request for quotations; and (2) two of the three solicitation amendments. The protester also requested reimbursement for its protest preparation costs. GAO held that the protester: (1) untimely filed its protest more than 10 days after it knew the basis for protest...

  • pdf icon View Decision (PDF, 3 pages)
B-230088, Apr 11, 1988, 88-1 CPD 355

B-230088: Apr 11, 1988

Protest concerning firm's failure to receive solicitation materials is dismissed as untimely when not filed within 10 working days of time protester knew or should have known of basis for protest. General Accounting Office (GAO) will not consider the merits of an untimely protest by invoking the significant issue exception in GAO Bid Protest Regulations where the protest does not raise an issue of...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap