[Protest of HHS Rejection of Bid for Chemical Testing]

B-229892: Mar 3, 1988

A firm protested the Department of Health and Human Services' (HHS) rejection of its bid for chemical testing, contending that HHS prematurely determined that its late bid did not represent a significant cost or technical advantage to the government to warrant its inclusion in the competitive range. GAO held that HHS: (1) properly evaluated the initial bid to make its determination; and (2) reason...

  • pdf icon View Decision (PDF, 3 pages)
B-229892, Mar 3, 1988, 67 Comp.Gen. 305

B-229892: Mar 3, 1988

Procurement - Competitive Negotiation - Offers - Late Submission - Acceptance Criteria DIGEST: A late proposal was properly rejected after the initial evaluation in accordance with alternate late proposal clause. Five proposals were received by the closing date. GRI's proposal was received 1 day late. It was received before proposals were distributed for evaluation. Whichever is earlier. That is....

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap