The report you requested was not found, or there is more than one product with this report number. Please select from this list of similar report numbers.


[Protest of Any Air Force Contract Award for Airfield and Street Marking]

B-229818: Feb 23, 1988

A firm protested any contract award under an Air Force solicitation for airfield and street marking, contending that the solicitation called for inferior materials. GAO held that the protester, as a potential subcontractor, was not sufficiently interested to protest. Accordingly, the protest was dismissed...

  • pdf icon View Decision (PDF, 2 pages)
B-229818, Feb 23, 1988

B-229818: Feb 23, 1988

DIGEST: Protest is dismissed where the protestor is. Therefore is not an "interested party" under the Competition in Contracting Act. Because Flex-0-Lite is not an "interested party" under the Competition in Contracting Act (CICA). The term "interested party" is defined in the CICA as "an actual or prospective bidder or offeror whose direct economic interest would be affected by the award of the c...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap