B-229750.3:
Apr 13, 1988
A firm protested a Marine Corps contract award for computer graphics systems, contending that the awardee could not: (1) meet all of the specifications; or (2) perform the contract at its proposed price. GAO held that: (1) since the protester did not rebut the Corps' response to a prior protest allegation that the awardee could not meet the specifications, it abandoned that protest issue; and (2)...