B-229569:
Mar 11, 1988
A firm protested three Air Force contract awards for high power amplifiers, contending that the Air Force: (1) improperly determined that its technical proposal was deficient; (2) failed to inform it of the weaknesses in its design; and (3) improperly considered cost realism in evaluating bids. GAO held that the Air Force: (1) properly awarded the contracts to the technically superior offerers who...