B-229007:
Dec 14, 1987
A firm protested the Army's proposed split award of a contract for multi-line loops, contending that: (1) as low aggregate bidder, it was entitled to award for all three line items; and (2) its bid's qualification restricted award to all or none of the line items. GAO held that the protester: (1) intended its bid qualification to apply to the quantities of each of the line items, since it had prev...