B-228891:
Sep 3, 1987
A firm protested any Army contract award for maintenance services, contending that the Army improperly required bidders to estimate costs over the entire 3-year contract period, which included two option years, since it knew that it would not exercise the options. GAO held that: (1) it would not review the Army's decision to award a new contract for the work rather than exercise the option under t...