The report you requested was not found, or there is more than one product with this report number. Please select from this list of similar report numbers.


[Protest of Army Contract Award for Tank Power Units]

B-228318: Jan 25, 1988

A firm protested an Army contract award for tank power units, contending that the Army should have held discussions, since: (1) it did not advise offerers that it might make award on the basis of initial proposals; (2) discussions would have provided it the opportunity to significantly reduce its bid price; and (3) its total bid price for the basic contract plus an option quantity was lower than t...

  • pdf icon View Decision (PDF, 4 pages)
B-228318, Jan 25, 1988, 88-1 CPD 66

B-228318: Jan 25, 1988

PROCUREMENT - Competitive Negotiation - Contract Awards - Initial Offer Awards - Propriety DIGEST: Protest against award of contract on the basis of initial proposals is denied where the solicitation advised offerors of that possibility and the existence of adequate competi-tion demonstrated that acceptance of the most favorable initial proposal would result in the lowest overall cost to the gover...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap