[Protest Against Army Contract Award]

B-228201: Sep 30, 1987

Additional Materials:


Office of Public Affairs
(202) 512-4800

A firm protested a proposed Army contract award to another firm, contending that the proposed awardee's bid was nonresponsive, since it failed to furnish proof that the signatory was its authorized agent. GAO held that failure to furnish proof of a signatory's authority prior to bid opening did not render the bid nonresponsive. Accordingly, the protest was dismissed.

Mar 15, 2018

  • ORBIS Sibro, Inc.
    We sustain the protest in part and deny it in part.