B-228138:
Oct 27, 1987
A firm protested the first and second low bidders' performance and payment bonds under a Navy solicitation for asbestos removal, contending that the bond sureties were inadequate. GAO held that: (1) whether the eventual awardee met the bonding requirements was a matter of contract administration, which it would not consider; and (2) the protester did not allege that the low bidders' bid bonds were...