B-227965.3:
Nov 23, 1987
A firm protested the Military Sealift Command's (MSC) decision not to contract for the operation and maintenance of two hospital ships, contending that MSC: (1) underestimated the crew required to adequately perform maintenance and repair tasks; and (2) failed to include a cost factor for defective performance by MSC personnel. GAO held that: (1) the protester failed to show that MSC acted fraudul...