B-227729:
Sep 10, 1987
A firm protested the Navy's rejection of its late bid for transformers, contending that the Navy's mishandling was the paramount cause of the late bid. GAO held that the Navy properly rejected the late bid, since the protester's commercial carrier did not deliver the bid to the proper location. Accordingly, the protest was denied...