[Protest of GSA Disqualification of Bidder as Nonresponsible]

B-227696: Sep 21, 1987

A firm protested the General Services Administration's determination that it was nonresponsible under a solicitation for furniture, contending that GSA: (1) improperly disqualified it, since it demonstrated its financial capability to perform; (2) arbitrarily required it to post a 30-percent performance bond; (3) should have allowed it to submit additional evidence regarding its responsibility; an...

  • pdf icon View Decision (PDF, 5 pages)
B-227696, Sep 21, 1987, 87-2 CPD 284

B-227696: Sep 21, 1987

The specific financial qualifications to be considered in determining a prospective contractor's responsibility are within the contracting officer's discretion and business judgement. A procuring agency is not required to delay award indefinitely while an offeror attempts to cure the causes for the firm being found nonresponsible and. Where a preaward survey found that an offeror's annual sales we...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap