B-225823.2:
Apr 28, 1987
A firm protested the General Services Administration's (GSA) rejection of its bid as late, contending that: (1) it mailed the bid in time to reach GSA prior to bid opening; and (2) GSA relied on alleged deficiencies in its performance on another contract to exclude it from this procurement. GAO held that GSA properly rejected the late bid, since: (1) federal government mishandling did not cause th...