B-225578.2:
Jul 1, 1987
A firm requested reconsideration of the dismissal of its untimely protest against a Navy solicitation. The protester had contended that: (1) the Navy improperly amended the solicitation to include interport differentials as an evaluation factor; and (2) it was entitled to reimbursement for its bid and protest preparation costs. GAO held that: (1) the awardee was the low bidder even without conside...