B-225367:
Dec 12, 1986
A firm protested the Army's rejection of its bid for a boring and milling machine as nonresponsive, contending that: (1) the solicitation specifications permitted consideration of additional descriptive literature after bid opening; and (2) the Army should have awarded it the contract since it was the low, responsive, responsible bidder. GAO held that the Army properly rejected the bid as nonrespo...