[Protest of Contract Award for Guided Missile Telemetry Sections]

B-225140.2: Mar 18, 1987

A firm protested a contract award for guided missile telemetry sections, contending that: (1) it interpreted the procuring agency's request for offer revival and updated proposals as a request for best and final offers; and (2) the agency improperly rejected its reduced bid without holding discussions. GAO held that the agency properly: (1) awarded the contract on the basis of initial proposals; a...

  • pdf icon View Decision (PDF, 3 pages)
B-225140.2, MAR 18, 1987, 87-1 CPD 301

B-225140.2: Mar 18, 1987

AGENCY WAS NOT REQUIRED TO CONDUCT DISCUSSIONS UPON RECEIPT OF THE LOWER PRICE IN VIEW OF THE RELATIVELY SMALL MONETARY SAVINGS. THE PROTEST IS DENIED. AYDIN VECTOR WAS AWARDED THE CONTRACT ON THE BASIS OF ITS INITIAL PROPOSAL. MICROCOM CONTENDS THAT THE AGENCY'S ORAL REQUEST FOR OFFER REVIVAL WAS ACCOMPANIED BY A REQUEST THAT ITS PROPOSAL BE UPDATED. THE PROTESTER ARGUES THAT THE AGENCY WAS OBLIG...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap