B-224512.3,B-224512.4:
Apr 17, 1987
A firm: (1) requested reconsideration of the denial of its protest against the Air Force's rejection of its bid for teleconferencing equipment as nonresponsive; and (2) protested a proposed contract award to the third low bidder under the same solicitation. GAO had denied the firm's original protest, since its bid did not contain adequate descriptive literature. In its request for reconsideration,...