Oct 21, 1986
A firm protested a GSA solicitation for custodial and related services, contending that, as the incumbent contractor, it was prejudiced because GSA: (1) failed to correct a wage determination problem that it raised in an earlier protest; and (2) added a provision to the solicitation that exceeded the government's minimum needs. GAO noted that the solicitation included an old wage determination sin...