B-224390:
Sep 10, 1986
A firm protested the Army's rejection of its low bid as nonresponsive, contending that its bid bond implied an obligation consistent with the required form for bid bonds and the Army should have awarded it the contract. GAO found that: (1) the solicitation cautioned that failure to furnish a bid bond in the proper form and amount might warrant rejection of the bid; (2) the protester did not submit...