B-224120:
Sep 5, 1986
A firm protested the Air Force's rejection of its nonresponsive bid and contract award to another firm for modular office structures, contending that the Air Force should have: (1) assumed that it would provide certain required bid items since the Air Force made similar assumptions regarding other bid items; and (2) invoked the bid mistake procedures to question bidders concerning the items they i...