B-223244.2:
Jun 30, 1986
A firm protested the rejection of its bid as nonresponsive because it included a restriction on bid disclosure, contending that it only intended to restrict the physical handling of the bid package, not the contents of the bid itself. GAO held that: (1) the procuring agency properly rejected the bid since the bid disclosure restrictions rendered it nonresponsive; (2) a bid must publicly disclose t...