B-222109.2:
May 21, 1986
A firm protested the Army's rejection of its bid for moving services as unbalanced, contending that the rejection was improper since its prices were neither overstated nor understated. GAO noted that, although the protester was the incumbent contractor, it submitted a bid that reflected significant start-up costs. GAO held that the Army properly rejected the bid as materially and mathematically un...