B-221889:
Jul 3, 1986
A firm protested a Navy contract award for water main construction, contending that its bid modification was late because of erroneous information the Navy gave it regarding the presence of a telex machine at the contracting facility. The protester attempted to send a bid modification via telegram before bid opening, but the Navy received the telegram after bid opening because its machine was inca...