B-220413:
Feb 19, 1986
A firm protested the Air Force's post-bid-opening solicitation cancellation, contending that: (1) the solicitation's failure to indicate estimated quantities instead of fixed quantities did not prejudice the bidders; and (2) the Air Force could meet its needs by awarding the contract. The protester also claimed reimbursement of its bid preparation costs. GAO has held that: (1) the use of specifica...