B-219981:
Nov 27, 1985
A firm protested a Marine Corps contract award to another firm for reflectometers, contending that the Marine Corps improperly allowed the awardee to correct a mistake in its bid. GAO held that the Marine Corps acted improperly in allowing the awardee to correct the bid error because: (1) the intended bid was not apparent from the face of the bid; (2) the awardee did not supply sufficient evidence...