B-219804:
Dec 4, 1985
A firm protested the Army's rejection of its bid as technically unacceptable and a proposed contract award, contending that: (1) the Army did not allow sufficient time for the preparation of proposals and failed to conduct adequate discussions; (2) the rejection of its proposal must have been for reasons other than those cited; and (3) the awardee's bid was unbalanced. GAO found that: (1) the prot...