A firm requested that GAO reopen the file on its protest under a federal agency solicitation. GAO had closed the file because the protester failed to timely file comments after it received the contracting agency's protest report. In its request, the protester contended that it did not receive the agency report until after the date GAO assumed it would. GAO held that the protester failed to meet it...