B-219644.4:
Jul 7, 1986
The Army requested reconsideration of a decision which sustained a protest against its contract award for telephone systems. GAO had: (1) held that the Army erred in rejecting the protester's bid for a system that required additional equipment to ensure its technical acceptability because it did not inform the protester that the bid was deficient; (2) recommended that the Army not exercise any del...