B-218352.2:
Apr 17, 1985
A firm requested reconsideration of a decision dismissing its protest as untimely. The firm requested reconsideration on the ground that the procurement reflected significant deficiencies. GAO may consider an untimely protest that raises issues significant to the procurement only when the issue is of widespread interest to the procurement community and has not been the subject of prior GAO decisio...