B-217286:
Apr 26, 1985
A firm protested a proposed Air Force contract award, alleging that the Air Force improperly allowed another firm to correct its bid after bid opening. The Air Force responded that the errors did not make the bid nonresponsive because the correct figures were easily obtained. The contracting officer requested and obtained a verification of the bid from the firm and the extended bid prices were the...