B-216707:
Apr 1, 1985
A firm protested an Army contract award, arguing that: (1) the awardee was improperly permitted to correct a bid error; and (2) the awardee's bid was unbalanced and should have been rejected as nonresponsive. GAO held that the agency reasonably allowed correction of the error because the bid clearly indicated that the error was made, how it occurred, and the amount of the intended bid. GAO also he...