B-216356:
Sep 24, 1984
A firm protested a contract award to another firm under an Air Force solicitation, contending that various improprieties may have occurred during contractor selection. GAO noted that the protester had made no effort to obtain information pertaining to the procurement from the Air Force. In addition, GAO held that the protest was untimely filed since it was not received by GAO until more than a mon...