B-216190.2,B-216190.3:
Apr 8, 1985
Two firms protested the General Services Administration's (GSA) reopening of negotiations in connection with its award to them of a multiple award Federal Supply Schedule contract. As a result of a protest from an unsuccessful bidder, GSA determined that the procurement had violated its policy on negotiating multiple award Schedule contracts. GAO held that the GSA decision to reopen negotiations w...