[Request for Reconsideration of Protest]

B-215915.2: Nov 21, 1984

A firm requested reconsideration of the GAO dismissal of its protest of a Coast Guard contract award. Although the Coast Guard had rejected the protester's bid as late, this determination was not questioned in the initial protest; rather, the protester had alleged that the awardee failed to conform to solicitation specifications. GAO had concluded that the protester was not an interested party und...

  • pdf icon View Decision (PDF, 3 pages)
B-215915.2, NOV 21, 1984, 84-2 CPD 546

B-215915.2: Nov 21, 1984

PRIOR DECISION IS AFFIRMED ON RECONSIDERATION WHERE PROTESTER HAS NOT SHOWN ANY ERROR OF LAW OR FACT WHICH WOULD WARRANT REVERSAL OF THE DECISION. PROTEST THAT AWARDEE MIGHT PROVIDE A NONCONFORMING ITEM RAISES A MATTER OF CONTRACT ADMINISTRATION WHICH IS THE RESPONSIBILITY OF THE PROCURING AGENCY. WE CONCLUDED SEI WAS NOT AN INTERESTED PARTY UNDER OUR BID PROTEST PROCEDURES TO CHALLENGE THE AWARD...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap