B-215873:
Feb 4, 1985
A firm protested a solicitation for dredging services issued by the Army Corps of Engineers and contract award to any other firm, contending that the solicitation specifications were unduly restrictive. The protester's bid had been rejected as nonresponsive because it offered equipment other than that required by the solicitation specifications. A contracting agency has the primary responsibility...