B-215505:
Feb 19, 1985
A firm requested reconsideration of a decision concerning work that it performed for the Veterans Administration (VA) without a contract. The requester had been allowed a partial recovery on a quantum meruit basis for the amount that it claimed; however, it challenged the quantum meruit method in this case and complained that it was entitled to other indirect costs as well as anticipated profits a...