B-214467:
Jun 27, 1984
A firm protested the rejection of its bid under an Army solicitation, contending that the Army improperly rejected the bid as nonresponsive. The protester also claimed reimbursement for bid preparation costs. The protester: (1) interpreted the solicitation as requiring completion of the contract within 60 days; (2) bid a performance period of 60 days; (3) noted that the Army had awarded it contrac...