[Protest Alleging Defective Marine Corps IFB]

B-213722: Dec 12, 1983

A firm protested that a solicitation issued by the Marine Corps was defective in several respects. Bid protest procedures require that a protest alleging improprieties in a solicitation which are apparent prior to bid opening be filed before that event. Since the firm filed its protest after bid opening, it was untimely. Accordingly, the protest was dismissed...

  • pdf icon View Decision (PDF, 1 pages)
B-213722, DEC 12, 1983

B-213722: Dec 12, 1983

DIGEST: PROTEST THAT IFB IS DEFECTIVE FILED AFTER BID OPENING IS UNTIMELY. IS DEFECTIVE IN SEVERAL RESPECTS. BID OPENING WAS OCTOBER 29. OUR BID PROTEST PROCEDURES REQUIRE THAT A PROTEST ALLEGING IMPROPRIETIES IN AN IFB WHICH ARE APPARENT PRIOR TO BID OPENING BE FILED BEFORE BID OPENING. 4 C.F.R. IT IS UNTIMELY...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap