The report you requested was not found, or there is more than one product with this report number. Please select from this list of similar report numbers.


[Protest of USDA Contract Award]

B-212571: Aug 25, 1983

A firm protested a Department of Agriculture contract award, contending that various specifications in the solicitation were either too restrictive or not definitive enough. These allegations concerned improprieties in the solicitation which were apparent prior to bid opening and were required to be submitted prior to the date set for bid opening. Since this protest was filed after that date, it w...

  • pdf icon View Decision (PDF, 1 pages)
B-212571, AUG 25, 1983

B-212571: Aug 25, 1983

DIGEST: PROTEST ALLEGING DEFECTIVE SPECIFICATIONS IS DISMISSED AS UNTIMELY WHEN NOT RECEIVED BY CONTRACTING AGENCY OR GAO PRIOR TO THE TIME SET FOR BID OPENING. EATON ESSENTIALLY COMPLAINS THAT VARIOUS SPECIFICATIONS IN THE SOLICITATION WERE EITHER TOO RESTRICTIVE OR NOT DEFINITIVE ENOUGH. THESE ALLEGATIONS CONCERN IMPROPRIETIES IN THE SOLICITATION WHICH WERE APPARENT PRIOR TO BID OPENING. WERE RE...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap