B-212534:
Nov 29, 1983
A firm protested any contract award by the Army under a solicitation for refuse collection trucks, containers, and data. The Army issued an amendment to the solicitation 2 days before the scheduled bid opening, which altered the specifications and extended the bid opening date. The protester's bid was erroneously opened on the original bid opening date, and the protester contended that the Army sh...