B-212494.2:
Oct 14, 1983
A firm requested reconsideration of a decision which dismissed as untimely its protest of a Department of Transportation contract award. The requester argued that it did not actually protest the award and that it was unaware of the bid protest procedures timeliness requirements. GAO held that the requester knew of the basis of its protest more than 10 working days before its initial complaint but...