B-211942,B-211942.2:
Oct 24, 1983
Two firms protested a contract award by the Army to another firm, alleging that they were excluded from bidding. Prior to the scheduled bid opening, both protesters were notified orally that an amendment to the solicitation would be issued and that the bid opening date would be extended. The contracting officer did not become aware of the proposed amendment until the scheduled bid opening date, de...