B-211934.3:
Aug 26, 1983
A firm requested reconsideration of a GAO decision to dismiss its protest of a Navy contract award, because GAO viewed the protest as involving an affirmative determination of responsibility which it does not review under the circumstances applicable in this case. The protester contended that the GAO decision was wrong and stated that the protest involved responsiveness rather than responsibility...