The report you requested was not found, or there is more than one product with this report number. Please select from this list of similar report numbers.


[Protest of Air Force Contract Award Alleging Awardee's Bid Nonresponsive]

B-211899: Jun 27, 1983

A firm protested an Air Force contract award under an invitation for bids (IFB) for in-flight system console operations. The protester contended that the awardee's bid was nonresponsive because the firm failed to submit a quality control program with its bid as required by the IFB. GAO has held that such information may be required under an IFB to determine a bidder's responsibility; however, such...

  • pdf icon View Decision (PDF, 2 pages)
B-211899, JUN 27, 1983

B-211899: Jun 27, 1983

TECOM CONTENDS THAT THE AIR FORCE SHOULD HAVE DETERMINED LEAR SIEGLER'S BID TO BE NONRESPONSIVE BECAUSE LEAR-SIEGLER FAILED TO SUBMIT A QUALITY CONTROL PROGRAM WITH ITS BID AS REQUIRED BY THE IFB. WE HAVE HELD THAT WHILE INFORMATION AS TO HOW BIDDERS PROPOSE TO COMPLY WITH QUALITY CONTROL REQUIREMENTS FOR SERVICES MAY BE REQUIRED UNDER AN IFB TO DETERMINE A BIDDER'S RESPONSIBILITY. THIS IS SO REGA...

  • html report icon View Decision (HTML)
U.S. Government Accountability Office (GAO)
  • Press Center
  • Copyright & Terms of Use
  • FOIA Requests
  • Contact Us
  • Privacy Policy
  • Scam Alerts
  • Inspector General
  • Accessibility
  • No FEAR Act Data
  • Restricted Reports
  • Sitemap