B-209446:
Mar 24, 1983
A firm protested a proposed Air Force contract award for the construction of a commissary, contending that the awardee was nonresponsive because it submitted a defective bid bond. The solicitation required each bidder to submit a bid bond with its bid and stated that failure to furnish the bond could be cause for the bid's rejection. The protester contended that the the awardee's bond was ambiguou...