B-209351:
May 27, 1983
A firm protested certain solicitation specifications by the Army Corps of Engineers for the manufacture and installation of four hydraulic pump-turbines which required 100-percent domestic component content. After filing its protest with GAO, the firm filed suit against the Corps in the U.S. Claims Court which ordered the Corps to delay further action on the procurement pending a GAO decision. The...