B-208777:
Aug 30, 1983
A firm protested a Corps of Engineers contract award for a study of the probability of hazardous substance spills on a river system. The protester contended that, by awarding a firm fixed-price contract on the basis of initial proposals without discussions, the Corps awarded the contract to a firm that submitted a proposal that was higher priced and technically inferior to its own. In addition, th...